Advertisement
trendingNowenglish2353264https://zeenews.india.com/india/good-news-for-delhiites-this-flyover-to-decongest-traffic-in-delhis-narela-bawana-2353264.html

Good news for Delhiites, this flyover to decongest traffic on Delhi's Narela-Bawana route

The length of the straight portion of the road overbridge is 1680 metres and is built at a cost of Rs 389 crore.

Good news for Delhiites, this flyover to decongest traffic on Delhi's Narela-Bawana route Representational Image (PTI)

New Delhi: Union Minister Hardeep S Puri on Tuesday (April 6, 2021) virtually inaugurated a flyover-cum-road overbridge (ROB) that is going to decongest traffic in Delhi's Narela and Bawana and will provide smooth connectivity between the two densely populated areas.

The length of the straight portion of the ROB is 1680 metres and is built at a cost of Rs 389 crore. The project is funded by the Urban Development Fund (UDF) of the Union Ministry of Housing and Urban Affairs.

"This flyover cum ROB is in sync with a plan to decongest Delhi and put special emphasis on the development of Narela," the Ministry of Housing & Urban Affairs.

This is to be noted that there used to be traffic congestion in the area as railway crossing was a bottle-neck on the route and over 150 trains pass through this busy crossing every day.

As per the Ministry of Housing & Urban Affairs, about 80,000 car users use this crossing daily, making it one of the busiest railway crossings. 

Some of the salient features of ROB Narela are as below:

1. A Road Over Bridge cum Fly Over has been constructed by DDA at Narela on Urban Extension Road -1, around 2.5 km from the NH-44, connecting NH-44 (GT Karnal Road) and Bawana-Auchandi Road.

2. A stretch of 10.6 km length of UER-I from NH-44 to Auchandi has been completed. UER-1 is planned to ultimately connect up to NH-8. In order to improve the capacity of this corridor, it is further proposed to make the UER-1 signal free from NH-44 to Western Yamuna Canal by introduction of U-turns at strategically planned locations.

3. The Road Over Bridge has provision for two separate carriageways of 25.5 m each, consisting of 3 lane carriageway, dedicated bus lane, cycle track, utility corridor and footpath with patterned colour concrete.

4. The bridge has been constructed with RCC piers, pre-stressed girders, RCC slabs in 735 m length and 945 m long RE walls in approaches.

5. Around 200 octagonal poles with energy savings LED lights illuminate the bridge uniformly at night.

6. Indication boards on Overhead Gantries at both the approaches as well as sideboards along the bridge have been provided to guide commuters.

7. Arrangements have made for proper drainage and harvesting of Rainwater from the ROB through Rainwater Harvesting Structure.

Stay informed on all the latest news, real-time breaking news updates, and follow all the important headlines in india news and world News on Zee News.

NEWS ON ONE CLICK